ANDRA update EDRAM Paris PierreMarie ABADIE ANDRA CEO
ANDRA update EDRAM Paris Pierre-Marie ABADIE ANDRA -CEO EDRAM December 9, 2016 DINT/16 -0238
International review DINT/16 -0238 EDRAM December 9, 2016 2
Act on reversibility DINT/16 -0238 EDRAM December 9, 2016 3
Reversibility http: //www. andra. fr/download/andra-international-en/document/577 va. pdf DINT/16 -0238 EDRAM December 9, 2016 4
Act on reversibility – 11 July 2016 Reversibility of geological disposal is defined as The ability for successive generations either to continue the construction and then to operate the successive phases of a disposal, or to re-evaluate the choices defined previously and to make evolve the management options Validation of the Industrial Pilot Phase Governance of the Cigéo project Further vote in the Parliament following the Industrial Pilot Phase Update of the Master Plan of Operations and review every 5 years Review of the implementation of the principles of reversibility every 5 years, in connection with all other regulatory reviews DINT/16 -0238 EDRAM December 9, 2016 5
Public involvement DINT/16 -0238 EDRAM December 9, 2016 6
Public involvement in future steps Before the license application Public inquiries included in some regulatory procedures (archeology, underground investigations) Before granting the license Specific public inquiry Opinion of territorial representatives After commissioning of Cigéo Vote in the Parliament after the Industrial Pilot Phase Updates and reviews of the Master Plan of Operations throughout the life of Cigéo Reviews on reversibility DINT/16 -0238 EDRAM December 9, 2016 7
Consultation on Cigeo Before the License Application At the local level Involve the range of local stakeholders in the major aspects of the project affecting the region Impact assessment: consult on how to manage the impacts of the project and involve local stakeholders and members of civil society in the mitigation and compensation actions Links between sites: involve local stakeholders in the choice of technical solutions for the connection between the two surface areas (roadway, semi-buried or overhead conveyor belt) Feed urban development and environmental choices related to the project Share experience of major worksites with the local authorities within the Regional Workshops Jointly put together the Regional Development Contract (coordinated by the office of the Prefect) Technical workshops : water, roads, energy Specific workshops : economic development, training, research and innovation… DINT/16 -0238 EDRAM December 9, 2016 8
Consultation on Cigeo Before the License Application At the national level Input data into the Master Plan of Operations up to the license application What is the Master Plan of Operations? Andra produced a V 1 of the Cigeo Master Plan of Operations (PDE) on the basis of the studies conducted up until 2015 Its objective » To put the operational life of the project – and beyond – into perspective, through its various milestones » Enable future generations to see the decisions that they will have to / could take A vocation » Be a governance tool for Cigeo, to enable future generations to take decisions in the best possible conditions In this respect, it must make it possible to: » Track the decisions taken or to be taken throughout the life of the installation » Define the means of involving society in the various milestones / according to the decisions to be taken during the life of the project and the information that Andra is required to transmit DINT/16 -0238 EDRAM December 9, 2016 9
The PDE Will Change Throughout the Consultation Andra submitted a V 1 of the PDE to ASN in April 2016. The PDE will be the subject of consultation in order to meet 2 objectives: Share and enhance the proposed PDE Use language that is accessible and comprehensible to everyone Ensure a sufficient level of information and propose a structure that will be able to accommodate changes Define the practical and operational methods of governance of the installation Methods to be determined with the project stakeholders Who to involve, when, how, in what conditions and with what resources A formalised, shared governance system to be submitted to the supervisory body and to Parliament It will be subject to change up until submission of the license application The PDE itself will be included in the license application file foreseen in 2018 DINT/16 -0238 EDRAM December 9, 2016 10
After the Licensing Decree (If Granted) The PDE will serve as a concrete tool in the governance process The PDE will be periodically concerted with the public and updated within the governance process Before the start of nuclear operations Following the industrial pilot phase At least every five years and at any major decision influencing Cigéo The legislative process also includes a formal opinion of the territorial communities following the industrial pilot phase DINT/16 -0238 EDRAM December 9, 2016 11
The Industrial Pilot Phase DINT/16 -0238 EDRAM December 9, 2016 12
The Industrial Pilot Phase defined in the 2016 Act After licensing « The operation starts with an Industrial Pilot Phase to consolidate the reversibility and the demonstration of safety, including a program of field tests. All waste packages must remain easily retrievable during this phase. The pilot phase includes retrieval tests» Foreseen process Andra will report the results of the Industrial Pilot Review by the Regulator and other relevant bodies New Act to be submitted by the Government to the Parliament Issuing the license for full operation of the facility by the regulator DINT/16 -0238 EDRAM December 9, 2016 13
Industrial Pilot Phase Cigéo after Completion (2145) Lay out of the Underground Facility during the Industrial Pilot Phase Cigéo 2031 DINT/16 -0238 EDRAM December 9, 2016 14 14
Industrial Pilot Phase The Industrial Pilot Phase aims to complement URL tests in order to consolidate in real conditions: Safety in operating conditions Performances of industrial equipments Retrievability of waste disposal packages Ability to monitor facilities Ability to close and seal access drifts, ramps and shafts Technical routes for future optimization, such as Potentially increased diameter of ILW disposal vaults Potentially increased length of HLW disposal cells DINT/16 -0238 EDRAM December 9, 2016 15
Industrial Pilot Phase Two types of tests will be carried out: Construction and operation of a first phase of industrial facilities: Waste reception, preparation and emplacement ILW disposal vaults, including reinforced monitoring systems HLW disposal cells 1. Inactive start tests (using inactive waste package models) 2. Commissioning tests with real waste packages 3. Gradual increase of the operating rate Full scale inactive demonstration tests DINT/16 -0238 EDRAM December 9, 2016 16
Industrial Pilot Phase Full scale inactive demonstration tests DINT/16 -0238 EDRAM December 9, 2016 17
Cigéo Project Life Cycle DINT/16 -0238 EDRAM December 9, 2016 18
Integration of the project Cigéo in the territory Input data DINT/16 -0238 EDRAM December 9, 2016 19
Aim of the document submitted in June 2016 Photo of the Cigéo project and its needs at the end of the preliminary design studies Common knowledge of the project, part of a more global approach of co-construction and co-development of a territory project It is not meant to be exhaustive, and is not an end in itself. It does not present the security options (object of the security option file) nor the impacts of the project (impact study) DINT/16 -0238 EDRAM December 9, 2016 20
Industrial organization for the construction phase First reflection of a preferential scenario for the industrial organization of Cigéo: new approach and new calls for tender ANDRA, PROJECT OWNER PROJECT MANAGEMENT MAIN CONTRACTOR surface traditional works/transversal works ………………… WASTE PACKAGE, design, production TURNKEY (GENERAL CONTRACTOR+EQUIPM ENT MANUFACTURER) DIGGING CONTRACTOR Equipped shafts EP 1 control system nuclear process surface and underground OFF-SITE LAYOUT (ELECTRICAL SUBSTATION, ROAD 960), , …) Ramps, drifts, disposal tunnels and cells RAILWAY CONNECTION (ITE) FUNICULAR (design, construction, maintenance and operation ) SPECIFIC TECHNICAL CONTRACTORS <MOe-P> , (Systra) Allotment perimeter to be refined DICOD/16 -0108 21
Jobs Consolidated staff Project owner + project management + contracting companies Begining of operations: stabilization around 600 workers 400 : operation 200 : underground facility Initial construction works: Max in 2022 : more than 2 000 workers during 5 years Preliminary amenities and preparation of start-up of the construction Rapid increase in staff : nearly 1, 000 people DICOD/16 -0108 22
Technical workshops for the integration of Cigéo in the territory Networks (under state responsibility) Water supply and discharge (2020) : 500 m 3/day during construction, and then 200 m 3/day Power supply, works to be started in 2018, 400 k. V/90 k. V Roads Other, to be managed by Andra Connexions between surface facilities Gas DINT/16 -0238 EDRAM December 9, 2016 23
Projects related to the development of the territory (1/2) Economic development Support for local development in the energy sector Technical needs during construction works and then during operations Later works by facilitating local companies involvement in nuclear services Preparing local companies to the operations All works related to Cigéo Nuclear works in the field of conditioning and packaging of waste Human capacity building Training and education, partnerships with local schools Continuous education Promote access for local jobseekers to jobs linked to Cigéo DINT/16 -0238 EDRAM December 9, 2016 24
Projects related to the development of the territory (2/2) Development of the living environment and attractiveness Environmental excellence of Cigéo Measures to reduce impacts and compensations Landscape integration and urban and environmental quality Monitoring and observation of the local environment (OPE) During construction works ( temporary infrastructures, amenities, housing) and in the long –term (housing and services) Contribute to the image of the territory (scientific showroom, promotion of industrial tourism) Information and consultation Inform local and regional interested parties Consult on specific amenities (biomass vs gas, urbanistic and environmental designs…) Co-construction of the territory development contract DINT/16 -0238 EDRAM December 9, 2016 25
- Slides: 25