American Council of Engineering Companies ACEC RiversideSan Bernardino
American Council of Engineering Companies ACEC Riverside/San Bernardino Chapter Meeting March 23, 2017 Tim Byrne, PE Project Delivery Manager cta cog san bernardino county transportation authority san bernardino council of governments
Agenda • SBCTA Background • Project Delivery • Freeways • Interchanges • Grade Separations • Transit & Rail • Doing Business with SBCTA 2
2
County Transportation Commission Council Of Governments Subregional Planning Agency Congestion Management Agency Transportation Authority 4
Agenda • SBCTA Background • Project Delivery • Freeways • Interchanges • Grade Separations • Transit & Rail • Doing Business with SBCTA 5
Project Delivery 6 40
Project Delivery • Responsible for the development and construction of highway improvements including: • Freeways/ Highways • Interchanges • Railroad Grade Separations 7
Project Delivery What we are doing… • Environmental Phase • Environmental/Engineering Studies • Design and Right of Way Phases • Land Surveys • Geometrics • Acquisition • Utility Coordination • Construction • Post Construction • Project Close out • Landscape 8
Agenda • SBCTA Background • Project Delivery • Freeways • Interchanges • Grade Separations • Transit & Rail • Doing Business with SBCTA 9
Freeway Mainline 10
Freeway Mainline 11
Freeway Mainline Mixed Flow Lane Addition PA&ED January 2017 Final Design Complete Summer 2018 Begin Construction Spring 2019 12
Freeway Mainline Current Phase Total Amount Open to Public 1 I-10 EB Truck Climbing Lane Planning $25. 0 M 2021 2 I-15 Corridor Express Lanes Environmental $371. 0 M 2024 3 I-10 Corridor Express Lanes Environmental $1. 85 B 2024 4 SR-210 Lane Addition Design / ROW $133. 3 M 2020 5 US 395 Widening Design / ROW $57. 6 M 2020 Close Out $207. 6 M 2015 Close Out / Landscape $326. 3 M 2014 Landscape $223. 4 M $3. 19 B 2007 Project Name 6 I-215 Bi-County HOV Gap Closure 7 I-215 Widening 8 SR-210 Freeway 13
Agenda • SBCTA Background • Project Delivery • Freeways • Interchanges • Grade Separations • Transit & Rail • Doing Business with SBCTA 14
Interchanges 15
Interchanges CM C G / Interstate 215 Barton Road Interchange s t r Sta n o i t 17 c u 20 r t s all n F Co 16
Interchanges Interstate 215 University Parkway Interchange California’s first Divergent Diamond Interchange 17
Interchanges I-10 Tippecanoe II 18
Interchanges I-15 / I-215 / Devore 19
Interchanges Project Name 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 a 19 b 20 21 I-10 / Mountain View I-10 / Mount Vernon I-10 / Monte Vista I-215 / University SR 60 / Archibald SR 60 / Central I-10 / Alabama I-10 / Cedar SR-210 / Baseline I-215 / Barton SR-210 / Pepper I-10 / University I-10 / Pepper I-15 / Baseline I-15 / I-215 / Devore I-15 / Ranchero I-10 / Cherry I-10 / Citrus I-10 / Tippecanoe II I-10 / Riverside I-10 / Wildwood Canyon Current Phase Planning Environmental Environmental Design / ROW Construction Construction ROW / Close Out / Landscape Close Out / Landscape Conceptual Total Amount Open to Public $3 M $37. 6 M $31. 3 M $5. 6 M $14. 6 M $20 M $10. 0 M $72 M $19 M $43. 7 M $24. 5 M $5. 9 M $10. 5 M $50. 5 M $325 M $58. 3 M $80. 7 M $57. 7 M $24. 9 M $54. 2 M $40 M TBD $989 M 2020 2022 2021 2020 2021 2020 2019 2018 2017 2016 2015 2014 2016 2011 TBD 20
Agenda • SBCTA Background • Project Delivery • Freeways • Interchanges • Grade Separations • Transit & Rail • Doing Business with SBCTA 21
Grade Separations 22
Grade Separations Laurel Street / BNSF 23
Grade Separations Current Phase Total Amount Open to Public Environmental / Design $124 M 2024 2 Monte Vista Avenue / UPRR Construction $26. 7 M 2018 3 North Vineyard / UPRR Construction $56. 4 M 2016 4 Palm Avenue / BNSF Close Out $24. 2 M 2015 5 South Milliken / UPRR Close Out $72. 1 M 2017 6 Lenwood Road / BNSF Close Out $30. 9 M 2015 7 Laurel Street / BNSF Close Out $59. 9 M 2016 8 Hunts Lane / UPRR Close Out $34. 0 M 2014 9 Glen Helen Pkwy / BNSF Close Out $32. 5 M $460. 7 M 2015 Project Name 1 Mount Vernon Avenue Viaduct . 24
Agenda • SBCTA Background • Project Delivery • Freeways • Interchanges • Grade Separations • Transit & Rail • Doing Business with SBCTA 25
Transit & Rail Programs Responsible for the development and construction of transit related improvements and programs including: • Supporting Metrolink • Planning & implementing new passenger rail service including expansion of hybridrail service • Planning & implementing bus rapid transit service • Managing 62 miles of SBCTA owned railroad right-of-way 26
Transit & Rail Programs 27
Transit & Rail Programs Downtown San Bernardino Passenger Rail Project Construction = 70% complete Revenue service begins in spring 2017 28
Transit & Rail Programs Final Design 2015 -2017 Vehicle Procurement 2016 -2020 Construction 2017 -2019 Begin Service 2020 29
Transit & Rail Programs Gold Line Extension – Azusa to Montclair 30
Transit & Rail Programs West Valley Connector - BRT West Valley Connector 31
Transit & Rail Programs Current Phase Total Amount Open to Public Metrolink Eastern Maintenance Facility Operational $13. 1 M 2014 San Bernardino Transit Center Landscaping & Emergency Generator Operational $23 M 2015 Pre-Construction $0. 8 M 2017 Construction $110 M 2017 Design/Early Utilities Advanced Conceptual Engineering Environmental/ Preliminary Engineering $285. 5 M 2020 $70 M 2025 $74 M TBD Right of Way $4 M 2017 Pre-Construction $3. 7 M 2017 West Valley Connector Environmental $170 M+ TBD Zanja Bridge Removal Environmental $0. 06 M N/A Study $0. 3 M $754 M+ N/A Project Name Downtown San Bernardino Passenger Rail Redlands Passenger Rail Gold Line to Montclair* Metrolink Double Track – Lilac to Rancho Shortway Quiet Zone Sierra & Juniper Grade Crossings Mountain Transit Facility Upgrade Study 32
Transit & Rail Programs What’s next… • Downtown San Bernardino Passenger Rail Project • Complete construction & implement Metrolink Service • Redlands Passenger Rail Project • Complete final design on overall project • Award early utility relocation contract • Approve contract to purchase Hybrid-rail vehicles • Complete final design of the Hybrid-rail Maintenance Facility • Negotiate agreements with Omnitrans and Metrolink to operate and maintain Arrow Service 33
Transit & Rail Programs What’s next… • Secure environmental approval of the West Valley Connector and procure for right of way services • Complete construction of the SBTC Phase 2 • Support advanced conceptual engineering of Gold Line Phase 2 B to Montclair and seek remaining funding 34
Agenda • SBCTA Background • Project Delivery • Freeways • Interchanges • Grade Separations • Transit & Rail • Doing Business with SBCTA 35
Doing Business 36 36
Doing Business - Procurement • Proposals • Do your homework • Create strategic teaming opportunities • Understand your teams strengths and weaknesses • • • And your competition’s strengths and weaknesses! Review the evaluation criteria Check your references What value does your team offer SBCTA? Explain how relevant experience is relevant to this project Review your proposal • QA/QC discussion is meaningless if proposal contains a lot of grammatical/spelling errors • Be concise 37
Doing Business - Procurement • Interviews • Preparation shows • Be organized • Minimize distractions • Turn off cell phones, do not chew gum, take change/keys out of pockets • Anticipate and answer the entire question • Do not pile on • Respect the time • Q&A typically worth much more important than the presentation • PM is lead but have confidence in your team to do their part • If you bring them, let them speak • Why did you pick this team? 38
Doing Business - Procurement • Interviews • PM is lead, show confidence in your team to do their part • Sell yourself and your team • Why are you the best qualified team for this job? • • Speak to all panelists Use your time wisely Ask questions of procurement staff in advance of interview Strategize how you will close your interview, closing statements resonate with panelists 39
Thank You Questions/Comments Tim Byrne Project Delivery Manager tbyrne@gosbcta. com cta cog san bernardino county transportation authority san bernardino council of governments