AHCAL Integration JRA 3 Status and Outlook Mathias

  • Slides: 19
Download presentation
AHCAL Integration (JRA 3). Status and Outlook Mathias Reinecke for the AHCAL developers EUDET

AHCAL Integration (JRA 3). Status and Outlook Mathias Reinecke for the AHCAL developers EUDET annual meeting Geneva, Oct. 19 th – 21 st, 2009

Outline > JRA 3 Hardware Developments at DESY § CALIB, POWER, Flexleads § HBU

Outline > JRA 3 Hardware Developments at DESY § CALIB, POWER, Flexleads § HBU 0 § DIF 0 and DAQ interface (USB) § Tiles integration ‘old-fashioned overview’ Flexleads > System Commissioning > The Next Generation > Conclusions and Outlook Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 2

Flexleads – SIGNAL and POWER > 20 pieces of each type finished. Flexlead Pre-Bending:

Flexleads – SIGNAL and POWER > 20 pieces of each type finished. Flexlead Pre-Bending: > Pre-bending procedure ok. Type: POWER ~22 mm Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 3

Flexleads – SIGNAL and POWER CALIB > About 80 connection cycles up to now

Flexleads – SIGNAL and POWER CALIB > About 80 connection cycles up to now - still ok. > Compensate HBU misalignments in distance. > Fulfill AHCAL height requirements. HBU > Tests ok concerning: § Signal allocation § Signal quality § Resistance for power Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 4

CALIB and POWER Modules CALIB module: 11 x 10 cm² POWER module: 12. 5

CALIB and POWER Modules CALIB module: 11 x 10 cm² POWER module: 12. 5 x 11 cm² ARM 7 µC > 4 Modules of both types finished, in operation. > First tests successful. Sizes and heights: To be adapted to ILC mechanics later. Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 5

HCAL Base Unit (HBU) setup 2 setups in operation 36 cm SPIROC 1 DIF

HCAL Base Unit (HBU) setup 2 setups in operation 36 cm SPIROC 1 DIF FPGA CALIB Connectors: Signal Power USB / DAQ Flexleads SPIROC 2 CALIB (fibres), ASCR Prague Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 6

Reflector Foil Assembly HBU backside Reflector Foil (assembled in 4 steps) Mathias Reinecke |

Reflector Foil Assembly HBU backside Reflector Foil (assembled in 4 steps) Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 7

Reflector Foil Assembly m m 5 2. Alignment pin Si. PM pins LED Alignment

Reflector Foil Assembly m m 5 2. Alignment pin Si. PM pins LED Alignment ‘Reflector Foil – HBU’ Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 8

Tile Assembly (the first 18) Assembled tiles ‘ just before soldering’. Mathias Reinecke |

Tile Assembly (the first 18) Assembled tiles ‘ just before soldering’. Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 9

Tile Map Each quadrant can choose between 3 Si. PM bias voltages Mathias Reinecke

Tile Map Each quadrant can choose between 3 Si. PM bias voltages Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 10

Commissioning – Signal Chain for LED operation “Full Operation Chain” Concept : December 2007

Commissioning – Signal Chain for LED operation “Full Operation Chain” Concept : December 2007 Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 11

LED Pulse shape (measured on HBU) VCALIB (~8. 2 V) TCALIB (40 ns LVDS

LED Pulse shape (measured on HBU) VCALIB (~8. 2 V) TCALIB (40 ns LVDS pulse) LED optical Output (PMT H 9858 -01) Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 12

Commissioning SPIROC 2 output: LEDs firing, 3 events (triggers), 18 tiles assembled Hit Bit

Commissioning SPIROC 2 output: LEDs firing, 3 events (triggers), 18 tiles assembled Hit Bit (internal channel trigger) Baseline Tiles with LED Light (SPIROC out) 1 event (36 chns) Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 13

Commissioning (status last Friday) SPIROC 2 output: LEDs firing, 2000 events (trig. ), 18

Commissioning (status last Friday) SPIROC 2 output: LEDs firing, 2000 events (trig. ), 18 tiles assembled Chn 34: Open SPIROC Input (pedestal) Chn 34: Biased Si. PM, LED active Labview Software extended to multi-cycle data taking => histograms we try to get single peak spectra now to get an idea about global channel gain and noise margin Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 14

Commissioning Slow Control : Read detector’s temperatures, voltages, currents HBU temperature profile VDDA, VDDD

Commissioning Slow Control : Read detector’s temperatures, voltages, currents HBU temperature profile VDDA, VDDD and currents Slow-Control: Still under test Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 15

The Next Generation (‘final’ ILC setup concept) Mechanical concept: K. Gadow Not in scale!

The Next Generation (‘final’ ILC setup concept) Mechanical concept: K. Gadow Not in scale! Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 16

The Next Generation Cassette (=slab) HBU SPIROC Sector Connecting Plate Not in scale!! Central

The Next Generation Cassette (=slab) HBU SPIROC Sector Connecting Plate Not in scale!! Central Interface Board with DIF, CALIB and POWER Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 17

The Next Generation HBU SPIROC LED Flexlead + tiny connector Tile with Si. PM

The Next Generation HBU SPIROC LED Flexlead + tiny connector Tile with Si. PM Not in scale!! Central Interface Board with DIF, CALIB and POWER Cooling Pipe Reflector Foil Cassette Bottom Plate Height pitch of 20 mm possible: HCAL-W, under invest. Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 18

Conclusions and Outlook > AHCAL prototype delivers first test-data from LED system. > British

Conclusions and Outlook > AHCAL prototype delivers first test-data from LED system. > British DAQ (hardware, DIF firmware) still has to be implemented. > Full equipment of HBUs with tiles very soon now. > DESY electron-testbeam preparation: => S. Christen: Labview extension for testbeam => small hardware changes (e. g. ext. trigger) => lab characterization of HBU (incl. LED system) > Redesign concepts of AHCAL modules are prepared now. > A lot of system’s and SPIROC analogue and digital tests ahead. Mathias Reinecke | EUDET annual meeting Geneva | Oct. 19 th, 2009 | Page 19