AFPC Policy Protect its personnel contractors 3 rd

  • Slides: 21
Download presentation
AFPC Policy • Protect its personnel, contractors, 3 rd parties and the environment against

AFPC Policy • Protect its personnel, contractors, 3 rd parties and the environment against the hazards of exposure to ionizing radiation due to AFPC activities. • Avoid uncontrolled releases of radioactive contaminated substances and to minimize the effects of past deposits • apply the principles of ICRP 60 for radiation protection ( justification of a practice, optimization of protection and dose & risk limitation) • avoid the need for classified radiological workers wherever reasonably practicable 6/15/2021 1

Clean up of NORM contaminated areas • Radiological surveys have identified AFPC areas which

Clean up of NORM contaminated areas • Radiological surveys have identified AFPC areas which have become contaminated with NORM. • AFPC procedure is applicable to all AFPC activities to decontaminate NORM affected areas. • define standards and ensure availability of resources for decontamination. 6/15/2021 2

Clean up of NORM contamination areas Typical clean up activities shall be controlled by

Clean up of NORM contamination areas Typical clean up activities shall be controlled by a defined work methodology: • A detailed execution plan • Proposed clean up criteria • Special measures 6/15/2021 3

NORM in Oil and Gas Industry • Releases of radioactivity with produced water •

NORM in Oil and Gas Industry • Releases of radioactivity with produced water • Radioactive surface contamination on production equipment • Radioactive sludges • Radioactive scales • Radioactive surface contamination on disused equipment 6/15/2021 4

6/15/2021 5

6/15/2021 5

NORM Remediation Programme • All NORM contaminated areas have been extensively investigated by SAEC.

NORM Remediation Programme • All NORM contaminated areas have been extensively investigated by SAEC. • As the Syrian regulatory body, SAEC stated the preferred options for the permanent management of NORM contaminated waste • The final option has been supported by the external consultants AEA technology. 6/15/2021 6

Main Concept • to have all NORM Remediation projects integrated into a larger Programme

Main Concept • to have all NORM Remediation projects integrated into a larger Programme of environmental remediation. • The AFPC Programme is designed to meet regulatory requirements and International Standards to acceptable levels at reasonable cost. 6/15/2021 7

Syrian Clean-up and Disposal Criteria for NORM contaminated soils: • At 0. 15 Bq/g

Syrian Clean-up and Disposal Criteria for NORM contaminated soils: • At 0. 15 Bq/g of Ra 226 or less no treatment required. • More than 5. 2 Bq/g of Ra 226 must be treated as radioactive waste. • Between 0. 15 Bq/g and 5. 2 Bq/g of Ra 226 need a special treatment on site to reduce exposure to a value 0. 1 m. Sv/y. 6/15/2021 8

The final option following recommendations by SAEC and AEA Technology, AFPC preferred route for

The final option following recommendations by SAEC and AEA Technology, AFPC preferred route for three NORM contaminated areas is engineered disposal mounds, while disposal the fourth is by stabilization in a landfill. 6/15/2021 9

Requirements for engineered mound disposal facilities • Provide isolation of the waste from the

Requirements for engineered mound disposal facilities • Provide isolation of the waste from the surrounding environment • Inhibit surface water infiltration into the waste • Inhibit erosion of the cover the waste • Maintain a separation between the waste and the ground water • Promote the drainage of water that infiltrates the wast out of the waste 6/15/2021 10

Requirements for engineered mound disposal facilities • inhibit human and animal intrusion through the

Requirements for engineered mound disposal facilities • inhibit human and animal intrusion through the cover into the waste • Maintain stability under foreseen subsurface and geologic condition • the site for a dedicated facility should above flood - plain levels 6/15/2021 11

6/15/2021 12

6/15/2021 12

6/15/2021 13

6/15/2021 13

Requirements for engineered mound disposal facilities • The facility should be able to cope

Requirements for engineered mound disposal facilities • The facility should be able to cope with major events(flood, earthquake, and fire) on a time-scale of > 200 years. • Performance requirements during construction use of reasonably available materials and machinery • Optimization of waste movement and keeping radiation dose to workers ALARA 6/15/2021 14

Engineered Disposal Pits All contaminated materials excavated and • removed to disposal pit Co-disposal

Engineered Disposal Pits All contaminated materials excavated and • removed to disposal pit Co-disposal of sludge ; encapsulation • Lined pits • Top liner Coarse rock buttress Perimeter ditch 1. 0 m Clean soil 1. 5 m 1. 0 m 5 m 10 m 3. 0 m NORM soil 5 m Lower liner 6/15/2021 15

Thayyem: channel / sludge materials removed to disposal pit 6/15/2021 16

Thayyem: channel / sludge materials removed to disposal pit 6/15/2021 16

6/15/2021 17

6/15/2021 17

El-Ward: lagoon materials removed to disposal pit NW of plant 6/15/2021 18

El-Ward: lagoon materials removed to disposal pit NW of plant 6/15/2021 18

6/15/2021 19

6/15/2021 19

6/15/2021 20

6/15/2021 20

6/15/2021 21

6/15/2021 21