ACQUATICS FACILITY STUDY City of Vincennes Department of Parks & Recreation

ACQUATICS FACILITY STUDY City of Vincennes Department of Parks & Recreation

Concerns and Problems with Rainbow Beach • Overall image is poor, facility is tired

Concerns and Problems with Rainbow Beach • Overall image is poor, facility is tired and no longer an attraction. The facility lacks vitality. • Visitors are being lost to other venues. • The condition of the bathhouse is substandard. • Without shade, the oversized concrete pool deck is oppressive in the summer heat. • Pool mechanical system is antiquated and is past its life expectancy. • The concrete deck all around the pools has an irregular surface at expansion joints and settlement cracks. • Water from both the competition and wading pools is circulated through a single circulation pump violating current swimming pool codes. • Maintaining chemical balance for this pool is difficult. • It is reported that the pool loses approximately 1”-2” of water overnight due to leaks in the pool system located under the concrete pool shell. City of Vincennes – Aquatic Facility Study

Recommendations 1. Slides and / or Diving Boards 2. Play Apparatus / Structure for

Recommendations 1. Slides and / or Diving Boards 2. Play Apparatus / Structure for all ages 3. Zero Depth Entry 4. Competition / Recreation Combination – Uniqueness of 50 Meter Pool 5. Upgraded Bathhouse 6. Improved Concessions 7. ADA Accessibility 8. Variety of Experiences – Water Basketball, Water Volleyball, Etc. 9. Shade Structures and Lounge Seating 10. Sound System and Wi-Fi 11. Planned Activities and Programs City of Vincennes – Aquatic Facility Study

Pool Amenities City of Vincennes – Aquatic Facility Study

Pool Amenities City of Vincennes – Aquatic Facility Study

Slides City of Vincennes – Aquatic Facility Study

Slides City of Vincennes – Aquatic Facility Study

Zero Depth Entry City of Vincennes – Aquatic Facility Study

Zero Depth Entry City of Vincennes – Aquatic Facility Study

Shade Structures City of Vincennes – Aquatic Facility Study

Shade Structures City of Vincennes – Aquatic Facility Study

Play Apparatus City of Vincennes – Aquatic Facility Study

Play Apparatus City of Vincennes – Aquatic Facility Study

Spray Parks City of Vincennes – Aquatic Facility Study

Spray Parks City of Vincennes – Aquatic Facility Study

Recreation/Competition Combination City of Vincennes – Aquatic Facility Study

Recreation/Competition Combination City of Vincennes – Aquatic Facility Study

Bathhouse, Locker Facilities and Party Facilities City of Vincennes – Aquatic Facility Study

Bathhouse, Locker Facilities and Party Facilities City of Vincennes – Aquatic Facility Study

Options for Rainbow Beach City of Vincennes – Aquatic Facility Study

Options for Rainbow Beach City of Vincennes – Aquatic Facility Study

Option A: Addition of a spray park to the existing facility City of Vincennes

Option A: Addition of a spray park to the existing facility City of Vincennes – Aquatic Facility Study

Option A: Addition of a spray park to the existing facility Description and Cost

Option A: Addition of a spray park to the existing facility Description and Cost 0 • Existing Recreation Pool and Bathhouse to Remain…………. . . . . …. . . . • Remove existing Wadding Pool and Deck……………………………. …. $ 10, 000 • Create New Splash Park……………. . ……………………………… $ 140, 000 • Provide Associated Site Improvements…………………. …. . $ 85, 000 $ 22, 000 Construction Range of Magnitude Budget………………. …. ……. . $ 257, 000 • Add new deck around the existing pool………………………………. ……. $ ? ? ? Shade Structures, Pavement, Fencing, Etc. • Contractor General Conditions/Overhead & Profit……………………. . City of Vincennes – Aquatic Facility Study

Option B: Renovation of the existing facility City of Vincennes – Aquatic Facility Study

Option B: Renovation of the existing facility City of Vincennes – Aquatic Facility Study

Option B: Renovation of the existing facility Description and Cost • Minor Renovations to

Option B: Renovation of the existing facility Description and Cost • Minor Renovations to Existing Bathhouse. ………………. …. . . . . $ 100, 000 • Renovation Existing 10 Lane 50 Meter Lap Pool………………. . …………………. . . $ 1, 800, 000 Shade Structures………………………. . … $ 810, 000 • Provide New Water Slide……………………………………. . . . $ 175, 000 -$300, 000 • New Water Features/Play Apparatus………………. . $ 165, 000 • Contractor General Conditions/Overhead & Profit. ……………………. . …. $ 305, 000 • Infill Diving Well, Create New Slide Well, Create Zero Depth Entry, New Pool Filtration & Chemical Systems, Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & Construction Range of Magnitude Budget………. …………………. . … $ 3, 355, 000 -$3, 480, 000 City of Vincennes – Aquatic Facility Study

Option B. 1: Renovation of the existing facility City of Vincennes – Aquatic Facility

Option B. 1: Renovation of the existing facility City of Vincennes – Aquatic Facility Study

Option B. 1: Renovation of the existing facility Description and Cost • Minor Renovations

Option B. 1: Renovation of the existing facility Description and Cost • Minor Renovations to Existing Bathhouse…………………. …. . . . . $ 100, 000 • Renovation Existing 10 Lane 50 Meter Lap Pool………………. . …………………. . $ 1, 800, 000 Shade Structures…………………………………………. . . $ 810, 000 • Provide New Water Slide……………………………………. . . $ 175, 000 -$300, 000 • New Water Features/Play Apparatus. ……………………………. . $ 165, 000 • Add Spray Park and Associated Site Improvements……………………. $ 160, 000 • Contractor General Conditions/Overhead & Profit…………………. . …… $ 321, 000 • Infill Diving Well, Create New Slide Well, Create Zero Depth Entry, New Pool Filtration & Chemical Systems, Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & Construction Range of Magnitude Budget……………………. … $ 3, 531, 000 -$3, 656, 000 City of Vincennes – Aquatic Facility Study

Option C: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

Option C: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

Option C: Construction of a replacement facility Description and Cost • Minor Renovations to

Option C: Construction of a replacement facility Description and Cost • Minor Renovations to Existing Bathhouse………………. …. . . . . $ 100, 000 • Create New Pool………………………………. . . . . $ 1, 250, 000 Shade Structures, etc……………………………. . . $ 740, 000 • Provide New Water Slide……………………………. . . . . $ 175, 000 -$300, 000 • New Water Features/Play Apparatus………………. . . $ 165, 000 • Contractor General Conditions/Overhead & Profit…………………. . . $ 243, 000 • Eight Lane – 25 Yard Lap Pool, Zero Depth Entry, Slide Well, New Pool Filtration & Chemical Systems, Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & Construction Range of Magnitude Budget………………. . . . . $ 2, 673, 000 -$2, 798, 000 City of Vincennes – Aquatic Facility Study

Option C. 1: Construction of a replacement facility City of Vincennes – Aquatic Facility

Option C. 1: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

Option C. 1: Construction of a replacement facility Description and Cost • Minor Renovations

Option C. 1: Construction of a replacement facility Description and Cost • Minor Renovations to Existing Bathhouse………………. …. . . . . $ 100, 000 • Create New Pool………………………………. . ……………… $ 1, 250, 000 Shade Structures, etc……………………………. . $ 740, 000 • Provide New Water Slide……………………………. . . . . $ 175, 000 -$300, 000 • New Water Features/Play Apparatus…. . …………………. . $ 165, 000 • Add Spray Park and Associated Site Improvements………………… $ 160, 000 • Contractor General Conditions/Overhead & Profit………………… $ 259, 000 • Eight Lane – 25 Yard Lap Pool, Zero Depth Entry, Slide Well, New Pool Filtration & Chemical Systems, Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & Construction Range of Magnitude Budget………………. . . . . $ 2, 849, 000 -$2, 974, 000 City of Vincennes – Aquatic Facility Study

Option C. 2: Construction of a replacement facility City of Vincennes – Aquatic Facility

Option C. 2: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

Option C. 2: Construction of a replacement facility Description and Cost • Minor Renovations

Option C. 2: Construction of a replacement facility Description and Cost • Minor Renovations to Existing Bathhouse………………. …. . . $ 100, 000 • Create New Pool………………………………. . ……… $ 2, 300, 000 Shade Structures, etc……………………………. . $ 810, 000 • Provide New Water Slide……………………………. . . $ 175, 000 -$300, 000 • New Water Features/Play Apparatus…. . …………………. . $ 165, 000 • Add Spray Park and Associated Site Improvements……………. . $ 160, 000 • Contractor General Conditions/Overhead & Profit…………………. . $ 371, 000 • Eight Lane – 50 Meter Lap Pool, Zero Depth Entry, Slide Well, New Pool Filtration & Chemical Systems, Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & Construction Range of Magnitude Budget………………. . $ 4, 081, 000 -$4, 206, 000 City of Vincennes – Aquatic Facility Study

Option C. 3: Construction of a replacement facility City of Vincennes – Aquatic Facility

Option C. 3: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

Option C. 3: Construction of a replacement facility Description and Cost $ 2, 300,

Option C. 3: Construction of a replacement facility Description and Cost $ 2, 300, 000 Shade Structures, etc……………………………. . $ 810, 000 • Provide New Water Slide……………………………. . . $ 175, 000 -$300, 000 • New Water Features/Play Apparatus………………. . $ 165, 000 • Add Spray Park and Associated Site Improvements………………. . $ 160, 000 • Add New Bathhouse with Concessions………………………. $ 625, 000 • Contractor General Conditions/Overhead & Profit…………………. . $ 423, 000 • Create New Pool………………………………. . ………… • Eight Lane – 50 Meter Lap Pool, Zero Depth Entry, Slide Well, New Pool Filtration & Chemical Systems, Piping & Equipment • New Equipment Building, MEP, Pool Deck, Fencing & Construction Range of Magnitude Budget………………. . . $ 4, 658, 000 -$4, 783, 000 City of Vincennes – Aquatic Facility Study

Cost Comparison City of Vincennes – Aquatic Facility Study

Cost Comparison City of Vincennes – Aquatic Facility Study

Cost Comparison of Other Facilities Baker Park Pool New Castle, Indiana Year Built Pool

Cost Comparison of Other Facilities Baker Park Pool New Castle, Indiana Year Built Pool S. F. Original Pool Cost 2012 Pool Cost Description 2007 7, 546 $999, 000 $1, 158, 000 25 yard pool, zero depth entry, small participatory feature, slide City of Vincennes – Aquatic Facility Study

Cost Comparison of Other Facilities Rochelle-Landers Pool Evansville, Indiana Year Built Pool S. F.

Cost Comparison of Other Facilities Rochelle-Landers Pool Evansville, Indiana Year Built Pool S. F. Original Pool Cost 2009 7, 966 $1, 152, 000 2012 Pool Cost $1, 258, 000 Description 25 yard pool, zero depth entry, large participatory play feature, tot slide, medium sized slide, spray park features in zero depth entry City of Vincennes – Aquatic Facility Study

Cost Comparison of Other Facilities Bethel Park Aquatic Center Indianapolis, Indiana Year Built Pool

Cost Comparison of Other Facilities Bethel Park Aquatic Center Indianapolis, Indiana Year Built Pool S. F. Original Pool Cost 2012 Pool Cost Description 2011 6, 691 $1, 146, 000 $1, 180, 000 25 yard pool, zero depth entry, large participatory play feature, “run-out” slide City of Vincennes – Aquatic Facility Study