Abstract Storage Ring Vacuum and Interface to Magnets
Abstract Storage Ring Vacuum and Interface to Magnets Hsiao-chaun Hseuh, NSLS-II Project This presentation provided a quick overview of the storage ring vacuum system for the NSLS II project. A typical cell layout was detailed including the various cross section shapes and materials, valve locations and types as well as the pumps and instrumentation used. In addition, the types and locations of the various photon absorbers and chamber interconnects were presented. The second half of the talk focused on interface between the various storage ring magnets and the vacuum chambers. Most of the problems encountered were caused by the lack of consistency in the coil shape and the positioning of the coils on the yokes. Providing the vendors with 'go-gauges' earlier in the project could have prevented some of the troubles we encountered. The importance of collaboration and communication between the various groups as well technicians and engineers was highlighted. Finally, the limitation on the extraction of ID and bending magnet fans due to the magnet dimensions as discussed. *Work performed under auspices of the United States Department of Energy, under contract DE-AC 0298 CH 10886
Storage Ring Vacuum and Interface to Magnets Prepared by: Charles Hetzel April 11 th, 2012
Storage Ring Vacuum and Interface to Magnets Presented by: Hsiao-Chaun Hseuh Prepared by: Charles Hetzel Magnet Workshop April 11 – 12, 2012
Outline § SR Cell Layout § Vacuum System Details § Chamber-Magnet Clearance § Collaboration and Communication § Specification
Facility Overview § Nominal energy: 3 Ge. V § Nominal current: 500 m. A 6 § 30 cells in 5 pentants § Ring circumference: 792 m 1 - Accelerator Tunnel 2 - Experimental Floor 3 - 200 Me. V LINAC 5 6 3 1 2 4 - 3 Ge. V Booster (C=158 m) 5 - RF Building, liquid He Plant 6 - Service Buildings 6 4 6 6
Typical Cell Layout § Each 19 -m cell (GV to GV) consists of 5 individual magnet/chamber girders. § 3 focusing and 2 bending segments. § With RF gate valves at both ends of the cell. § Photon extraction takes place at G 4 and G 6. § Each cell is in-situ bakeable to > 130 o. C § Design pressure: < 1 x 10 -9 Torr at 500 m. A. ID photon extraction G 2 Multipole G 3 Dipole 3 PW pho G 4 Multipole Fast corrector and RF gate valve ton extrac G 5 Dipole tion G 6 Multipole 3 pole wiggler (3 PW) Fast corrector and RF gate valve
Cell Chamber Extrusion Cross Sections S 4 A/S 5 A cross section Multipole cross section Dipole cross section Fast corrector Front End FC M D Dipol e FC M S D BM beam lin BM beam e line M Multipole • • ID/3 PW fans S ID beam line 90 multipole aluminum chambers, 3. 7 – 4. 5 m long 60 dipole aluminum chambers, 3 m long 60 short/narrow aluminum chambers - S 4 A, S 5 A 90 fast corrector inconel chambers - FC FC
Typical Cell Layout – Valves DN 100 RF gate valve 60 units § All metal RF gate valves isolate cells and straights. § Double position indicators. § Radiation resistant and bakeable. § Large RF gate valves to isolate SC cavities. § All metal gate valves at injectors and front ends. § Right angle valves § Roughing ports. § Vacuum gauge/RGA isolation. All metal gate valve ~ 40 units Right angle valve
Typical Cell Layout – Lumped Pumps and NEG Strips 100 l/s ion pump with TSP cartridge NEG strips in ante-chamber 200 l/s ion pump with TSP cartridge and roughing valve
Typical Cell Layout – Instrumentation § Instrumentation located at dipole chambers. § CCG and RGA at G 3 § CCG and TCG at G 5 § Gauge tree with isolation valve. Typical RGA scan RGA trend during bakeout
Typical Cell Layout – Absorbers Stick absorber, X = 22 & 25 mm < 700 W (< 5 W/mm 2) < 130°C, Tube < 119°C § Absorbers intercept unused dipole radiation. § Protect downstream flanges and bellows § All absorbers are made of Glid. Cop Al 15. Flange absorber 21 mm(V) X 64 mm(H) < 200 W (< 16 W/mm 2) Crotch absorber, X = +21 mm < 1800 W (< 57 W/mm 2) Glid. Cop < 180°C, Tube < 127°C
RF Shielded Bellows - > 220 units for Storage Ring inconel springs Requirements: § § Misalignment: +/- 2 mm Stroke: +10/-15 mm Angular deviation: +/-10 mrad Low impedance Stainless sleeve Glid. Cop fingers Water cooled flange Bellows weldment Stainless Sleeve (w Ag) Glid. Cop fingers Coil spring (Be-Cu) Finger retainer Contact springs Inconel 718 (w Ag)
Vacuum Chamber Cross Sections Dipole cross section Multipole cross section F M D Multipole Chamber in Sextupole S F M S D M Grooves are machined for magnet poles F
Chamber-Magnet Clearance § Chamber-Magnet pole clearance - ≧ 2 mm Not a lot when you consider: § Extrusion shape tolerance. § Bow and twist. § Distortion due to machining. § Machining tolerance. § Positioning according to BPM.
Chamber-Magnet Clearance § Grooves were machined to accommodate magnet poles for 2 mm clearance § But coil dimensions are not well controlled which caused interference. Current design Should have coil-chamber clearance of 4 mm. Machine grooves for coil clearance? Additional cost Chamber stability under vacuum
Chamber-Magnet Clearance § Clearance gauges should have been provided to manufacturers at the prototype stage. § Clearance check should have been added to the pre-ship check list for first articles. § Centering disk is required to ensure the profile is centered on pole tips. No centering disk = uneven gap With centering disk = even gap
Collaboration § Early and extensive collaboration with other groups. § Chamber design is driven by AP, Magnets, Diag. , etc. § Changes in BPM and mounting resulted in re-development of extrusion (> 1 yr). § Some chamber materials were changed § RF bellows for slow correctors § S 4 A material development (In ⇒ SS ⇒ Al) Original cross section § Inconel for FC chambers § RF shielding was added for BPM rogue modes. § Keep communication lines open § Attend other system meetings when possible. Current cross section § 3 -D modeling can’t identified interference during assembly § Difficult to replace BPM buttons on girders § Difficult to assemble bellows due to photon extraction pipes § Significant impact to vacuum chambers due to small changes in magnets. § Increase in quadrupole length – 6 completed chambers were re-machined! § Oversized coils in 90 mm dipoles – re-design chamber ports and stands
Communication § Pro-active communication and visits with manufacturers. § Establish relations with potential manufacturers as early as possible. § Visits early or before contracts are awarded can be very valuable § Is this allowed? § Encourage manufacturers to become more than manufacturers. § Ask manufacturer inputs to improve design and fabrication methods § Lack of quality control at some manufacturers – bi-metal flanges! § Close interaction between engineers and technicians. § Develop required tooling as soon as possible. § Use feedback from techs to improve and simplify the design and/or the fixtures. § Reference drawings are more useful to techs than a stack of engineering drawings. § Engineers should work through first few assemblies with technicians.
Specification Establish a clear and complete set of specifications early on. § These can drive fundamental choices that can’t be changed. § i. e. comprehensive ray tracings early on for all possible insertion devices and beam positions to define § Geometric envelope vs. beam acceptance for SRP § Protection of vacuum components from large beam deviation § Allowable current without active interlock during commissioning § Maximum photon extraction openings are limited by the outboard dimensions of the magnets QM 2: < - 2 mr for ID fan QL 2/QH 2: < - 5 mr for BM fan QM 2 QL 2
- Slides: 19