ABC 130 and HCC Submissions F Anghinolfi 080213
ABC 130 and HCC Submissions F. Anghinolfi 08/02/13 ABC Final Design Review 1
ABC 130 (& HCC) Submission on MPW • On MPWs – Regular MOSIS MPW on 4 th May 2013 (reachable for ABC 130, for HCC ? ) – Next regular MOSIS MPW on 4 th August 2013 (reachable for HCC) – Additional quantities on request (but costs) 08/02/13 ABC Final Design Review 2
ABC 130 Submission on … • Shared Engineering Run (ABC + TDCpix) – ABC : Shared Engineering run with the NA 62/TDCpix submission (forecast 1 Q 2013) – Additional Eng. Run wafers at 3. 6 KUSD each (120 chips/w) – Needs Synchro btw TDCpix(NA 62) and ABC (for submission in Feb-March. 2013, FDR January-Feb 2013 for both ASICs) 08/02/13 ABC Final Design Review 3
ABC 130 & HCC Submission Scenario 2 • Shared Engineering Run (ABC + TDCpix) Additional Eng. Run wafers at 3. 5 KUSD each (120 chips/w) Production Run wafers at 2. 5 KUSD each (120 chips/w) 08/02/13 ABC Final Design Review 4
ABC 130 & HCC Submission Scenario 2 • Shared Engineering Run (ABC + TDCpix) Eng. Run + 1 Production run = 3720 chips Eng. Run + 2 Production run = 6120 chips Eng. Run + 3 Production run = 8520 chips 08/02/13 ABC Final Design Review 5
Separate HCC Production • Option for HCC if ABC is submitted separately MPW Mosis : 40 chips @ 37 KUSD “Small Quantity Production” with MOSIS (one 24 wafers lot of HCC-mainly reticle) at 100 K-150 KUSD range (should provide much more ASICS than the 900 requested …. ) Addition of (worst case cost) 7000 ABC (on shared Eng. Run with TDCPix) delivery plus HCC small Production Run = (322 + 150) KUSD ~ 472 KUSD 08/02/13 ABC Final Design Review 6
ABC 130 &HCC Engineering Run • Engineering Run (ABC + HCC) – Additional Eng. Run wafers at 3. 5 KUSD each – Production Run wafers at 2. 5 KUSD each – HCC drives the schedule 08/02/13 ABC Final Design Review 7
ABC 130 &HCC Submission Scenario 3 • Engineering Run (ABC + HCC) – One engineering run comes short (but close. . ) to 7000 Cost 475 KUSD 08/02/13 ABC Final Design Review 8
ABC 130 Submission Scenario • ABC independent of HCC – Regular MOSIS MPW on 4 th May 2013 (reachable for ABC 130, probably not for HCC) – Shared Engineering run with the NA 62/TDCpix submission (forecast 1 Q 2013) • With HCC : – Engineering Run, attached to HCC schedule • Independent HCC : – Small quantity production possible through MOSIS 08/02/13 ABC Final Design Review 9