A 2 Operations Management Critical Path Analysis How

  • Slides: 28
Download presentation
A 2 Operations Management Critical Path Analysis

A 2 Operations Management Critical Path Analysis

How long will it take? n Walls have decided to launch a new Magnum

How long will it take? n Walls have decided to launch a new Magnum ice cream. Machine delivery will take 9 weeks, installation takes 5 weeks, staff recruitment 4 weeks and training a further week. Suppliers need 2 weeks lead time and the trial production run will take 2 weeks. n How long until the new magnums will be in the retailers fridges? n Answers? 22 weeks? Longer? Shorter? n n n

Prepare a grid. Activity Preceded by Duration A Delivery - 9 B Installation A

Prepare a grid. Activity Preceded by Duration A Delivery - 9 B Installation A 5 C Recruit - 4 D Train C 1 E Supply - 2 F Trial B, D, E 2

Answer

Answer

Critical Path Analysis n The process of planning the sequence of activities in a

Critical Path Analysis n The process of planning the sequence of activities in a project in order to discover the most efficient and quickest way of completing it. n Widely used in industries such as construction where it is possible to operate a range of activities in parallel n By mapping out the network of different activities firms can see which activities can be run at the same time n It also allows firms to see which activities can not be delayed without holding up the overall project

Critical Path Analysis involves constructing a network diagram. A node denotes the start and

Critical Path Analysis involves constructing a network diagram. A node denotes the start and finish of an activity. It is split into 3 sections Earliest start time Number of the (EST) that an activity node. Provides a can commence and 1 unique identity depends on the completion of the previous activity Latest finishing time (LFT) of the previous activity without delaying the next activity n n An arrow represents an activity which is labelled and put above the arrow. Each activity has a duration which is put underneath the arrow. A 5 days

This diagram represents a project with four activities - A, B, C and D.

This diagram represents a project with four activities - A, B, C and D. D can not start until C has been completed. B 1 A 2 C 3 D 4

Student activity n Draw a network using the following information: A, B and C

Student activity n Draw a network using the following information: A, B and C begin together. D follows A, E follows B, F follows C and E.

Answer A D B E C F

Answer A D B E C F

Constructing a critical path network n Prerequisite - the activity that must be completed

Constructing a critical path network n Prerequisite - the activity that must be completed before our selected activity can occur. E. g. digging foundations for a house before building the walls

Constructing a critical path network n Step 1: Draw a node to represent the

Constructing a critical path network n Step 1: Draw a node to represent the start of the network. All networks must start and end with a node. Do not draw a node at the end of an activity line immediately, ensure it is right first. A node represents the point at which a new activity can begin. n Step 2: Identify activities with no prerequisites. Draw lines from left to right from node 1. n Step 3: Label activity lines with description and duration n Step 4: Move onto the first activity with a prerequisite. Place a node at the end of the line and draw the next activity which is reliant on the previous activity being completed. n Step 5: Repeat steps 3 and 4 until complete. Then calculate the ESTs and LFTs. Then the critical path can be established.

Constructing the Critical Path Analysis n Earliest starting time (EST) - Move forward through

Constructing the Critical Path Analysis n Earliest starting time (EST) - Move forward through the nodes and always pick the largest of the options. Work right choosing the highest option for each node. n Latest finishing time (LFT) - move back from the final node and always pick the smallest of the options. Work left choosing the lowest option for each node.

The Critical Path n The sequence of activities that cannot be delayed without delaying

The Critical Path n The sequence of activities that cannot be delayed without delaying the overall completion of the project. n It is represented by activities that have identical LFTs and ESTs and it is the longest path between nodes.

Student activity - Complete the critical path analysis for the following project. Identify the

Student activity - Complete the critical path analysis for the following project. Identify the critical path.

Answer A 5 0 1 0 B 3 2 3 3 C 4 7

Answer A 5 0 1 0 B 3 2 3 3 C 4 7 3 7 D 2 The critical path is B, C, D 9 4 9

Tips n Always ask your self the question: What activity can I do next?

Tips n Always ask your self the question: What activity can I do next? n A node is like a full stop. It must go at the end of an activity, it does not represent an activity

Critical path analysis - Lesson 2 - Recap n Critical path analysis is a

Critical path analysis - Lesson 2 - Recap n Critical path analysis is a way of showing how a lengthy and complex project (e. g. a building project, marketing campaign) can be completed in the shortest possible time. n It shows which of the activities are ‘critical’ - this means that if these activities are delayed, then the project will not be able to be completed on time.

Student Activity - Produce a critical path for the following project. Identify the critical

Student Activity - Produce a critical path for the following project. Identify the critical path.

Answer Step 1 - Draw the activities and nodes in the correct order n

Answer Step 1 - Draw the activities and nodes in the correct order n Step 2 calculate the ESTs and LFTs n EST - Earliest the next activity can begin n LFT - latest finishing time that the previous activity can finish without delaying the next activity LFT = work backwards EST = Previous EST plus subtracting the activity from the activity length (between previous LFT if there is an node 1 and 2: 0 + 6 = 6) option choose the smallest value n 1 0 0 A 6 2 5 Node 1 always start with an EST of zero and should have an LFT of zero 6 B 6 7 C 3 D 4 14 F 15 4 3 11 E 11 8 5 19 G 19 2 6 EST 21 21 LFT If you have a choice between two different EST values as at node 4 choose the biggest

Step 3 - Label the Critical Path n The critical path is the sequence

Step 3 - Label the Critical Path n The critical path is the sequence of activities that cannot be delayed without delaying the overall project completion. n It is represented by the activities with identical ESTs and LFTs and the longest path between the nodes n The critical path for the previous example would be: Critical path A, C, E, G n n On the diagram the critical path activities will be symbolised with two lines through the activity line

Float Times n Float time - the amount of time that non-critical activities within

Float Times n Float time - the amount of time that non-critical activities within a project can be delayed without affecting the deadline for completion of the whole project. n Total float for an activity- the amount of time an activity can be delayed without delaying the whole project n Total Float for an activity= LFT -EST - duration of the activity n E. g. Activity D = 15 - 11 - 3 = 1 day n Therefore the activity may be delayed by 1 day without affecting the whole project

Critical Path Analysis n A Produce a critical path network for the following Marketing

Critical Path Analysis n A Produce a critical path network for the following Marketing campaign. Calculate the EST, LFT, critical path and total float for each activity

Calculating float times 0 1 0 B 3 2 3 3 Float for the

Calculating float times 0 1 0 B 3 2 3 3 Float for the activity = LFT – EST - Duration Float for this activity = 3 – 3 - 0 = 0 D 10 3 13 8 5 21 21 Float for this activity = 21 – 10 - 8 = 3

Float times for Marketing strategy activity n A=4 -0 -4=0 n B = 13

Float times for Marketing strategy activity n A=4 -0 -4=0 n B = 13 – 4 – 6 = 3 n C = 11 – 7 – 4 = 0 n D = 21 – 13 – 8 = 0 n E = 21 – 10 = 0 n F = 30 – 21 – 9 = 0 n G = 35 – 30 – 5 = 0

Student Activity n Complete the exam question 2 a) for January 2005 Unit 4

Student Activity n Complete the exam question 2 a) for January 2005 Unit 4 exam paper

Answer January 2005 Question 2 a)

Answer January 2005 Question 2 a)

Problems of using CPA n Can encourage rigidity n If every activity is strictly

Problems of using CPA n Can encourage rigidity n If every activity is strictly time-tabled a delay in a critical activity may result in a greater overall delay n CPA focuses on speed of completion rather than quality n CPA relies on estimated completion times n Complex projects may be difficult to produce n Sub-contractors are outside of the firms control and may not stick to deadlines n Supplies may be delayed

Business Implications of Critical Path Analysis 1. Read and highlight the information on the

Business Implications of Critical Path Analysis 1. Read and highlight the information on the business implications of using CPA 2. Complete questions 1 and 2 on the information sheet n For both critical path questions calculate all ESTs, LFTs, the critical path and the float time of each activity