121 05 02 Beam Transfer Line and Beam
121. 05. 02 Beam Transfer Line and Beam Absorber (BTLBA) Meiqin Xiao DOE CD-2/3 a Independent Project Review SC-2 January 29, 2020 A Partnership of: US/DOE India/DAE Italy/INFN UK/UKRI-STFC France/CEA, CNRS/IN 2 P 3 Poland/WUST
About me • Meiqin Xiao, Application physicist III – L 3 manager of Beam Transfer Line and Beam Absorber (BTLBA) – Relevant experience • More than 30 years worked in Accelerator Physics, Majoring in beam dynamics, lattice design and modelling. • 20 years at Fermilab • Two transfer line designs at Fermilab (1) Transfer line from Recycler to Main injector and upgrade of Recycler Ring for NOv. A project (2) Transfer line from Recycler to P 1 line for Mu 2 e and G-2 projects. 2 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Outline • • Scope/Deliverables Organization Requirements Interfaces Technical Progress to Date Cost/Schedule ESH Quality Assurance • Previous Reviews and Recommendations • Summary 3 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
WBS Definition • PIP-II-doc-599 – Define and maintain the Lattice of the Beam Transfer Line and the Beam Absorber Line. Specify the Beam Line components of both lines. Design, procurement, fabrication, and testing of Beam Transfer Line collimators and beam dumps. It includes a low power beam dump in line with the Linac and the main beam dump in the Beam Absorber line. 4 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Scope and Deliverables Charge #1 • 121. 05. 02 BTLBA (Beam Transfer line Beam absorber line) – 121. 05. 02 BTLBA Beam Transfer line Ø Beam optics lattice. Ø Beam line collimators ü Deliver 3 beam line collimators, 1 KW each – 121. 05. 02. 03 BTLBA Beam absorbers Ø Beam absorbers ü Deliver the main 25 KW Beam absorber and 1 movable 2 KW absorber – 121. 05. 02. 04 BTLBA – Gamma-t-Jump ØMI Gamma-t Jump ü Deliver and install 16 Gamma-t quads and 4 power supplies 5 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Charge #4 Organization WBS 121. 05. 02 Beam Transfer Line Beam Absorber M. Xiao WBS 121. 05. 02. 01 WBS 121. 05. 02. 03 WBS 121. 05. 02. 04 Project Management Beam Line Collimators Beam Absorbers Gamma T-Jump Meiqin Xiao (Application Physicist III) (Level 3 Manager) Vladimir Sidirov (Mechanical Engineer) (Level 4 Manager) Yun He(Mechanical Engineer) (Level 4 Manager) Igor Rakhno (Physicist) D. Capista (Eng. Physicist) (Level 4 Manager) Alex Chen (Mechanical Engineer) Raul Campos (Mechanical Engineer) Igor Rakhno (Physicist) 6 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Requirements • Physics Requirements drive Functional requirements (Parameters PRD in PIP-II-doc-4312, Functional requirement in FRS PIP-II-doc-2396) Requirement # Requirement Statement F-121. 5. 02 -A 001 F-121. 5. 02 -A 003 The TLBA shall provide H- beam transport from the end of the Linac to the Booster injection girder. The TLBA shall have an appropriate beam size for the given aperture in the beam pipe and components to transport the beam. The TLBA shall provide the specifications of the magnets and their power supplies. F-121. 5. 02 -A 004 The TLBA shall provide specifications and locations for BPM’s to the Instrumentation L 3. F-121. 5. 02 -A 005 The TLBA shall provide specifications and locations for BLM’s to the Instrumentation L 3. The TLBA shall provide specifications and locations for the transverse beam profile monitors to the Instrumentation L 3. The TLBA shall provide specifications and location for the laser-based transverse beam emittance monitors to the Instrumentation L 3. The TLBA shall provide collimators that efficiently remove stray particles and provide protection against uncontrolled losses. The TLBA shall provide a beam absorber that can handle the impact and dissipate the energy of the full beam power specified for injection into the Booster ring. The TLBA shall provide a low power beam absorber that is movable and can handle sufficient beam power for Linac commissioning. F-121. 5. 02 -A 002 F-121. 5. 02 -A 006 F-121. 5. 02 -A 007 F-121. 5. 02 -A 008 F-121. 5. 02 -A 009 F-121. 5. 02 -A 010 7 F-121. 5. 02 -A 011 The TLBA shall interface to the Linac in a manner that maintains Linac low-particulate ultra-high vacuum. F-121. 5. 02 -A 012 The TLBA shall connect to the Booster injection girder vacuum with conventional ultra-high vacuum design principles. F-121. 5. 02 -A 013 The TLBA shall provide the quadrupole magnets required for the gamma-t jump system in Main Injector. The quadrupole magnets shall have enough strength to provide a loss free transition crossing in Main Injector. F-121. 5. 02 -A 014 The TLBA shall provide the power supplies require to drive the gamma-t quadrupole magnets in Main Injector 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Charge #2 Interfaces • Interface Control Document in PIP-II Doc. DB-3232 – Unique L 3 -to-L 3 interface IDs – Defines interfaces, roles (owner /supplier /integrator), lists relevant documentation WBS 121. 6. 06 Booster Con. WBS 121. 3. 05 Magnets/PS WBS 121. 5. 03 BTLInst WBS 121. 5. 02 BTLBA WBS 121. 3. 06 Vac. 8 12/31/2021 WBS 121. 4. 07 Acc. Physics WBS 121. 3. 09 BI WBS 121. 3. 08 SS WBS 121. 3. 07 Cntrl. M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Beam transfer lines overview 25 KW Beam Dump Horizontal, Vertical Momentum (Horizontal) collimators 2 KW Removable Beam Dump 9 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Technical Progress to Date (1) - Lattice • Charge #1 Beam Transfer line to the Booster (BTL) Ø The lattice was redesigned due to the Booster construction strategy changed, and the constrains to avoid the interference between the BTL and the Booster ring. The lattice now is finalized • Beam absorber line (BAL) Ø Switch magnet- Septum for the BAL is placed 2 cells upstream. Another pair of switch magnet Septum is going to be placed in the last 2 straight section cells for the future Mu 2 e line. • • Provided the acceptable tolerances of the magnet and power supplies, based on the simulations of magnetic field errors and misalignments Examined the apertures, especially for the special magnets such as Fast corrector (Switch magnet), Larger aperture quads and Septum in the beam line. • Generated the survey files for CAD 3 D model. • Preliminary designs review completed on December 12, 2019 (PIP-II-doc-4318. ) 10 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Updated the Booster connection Charge #1 Dog-leg dipoles: Vertical bending angle: 38. 696 mrad ~2. 217 deg Booster ORBUMP magnet 9 m (requested clearance) 1. 8 m Booster Wall QB 1 BA 24 CHUTE TE QB 2 The last dipole in ARC 2 QB 4 22 mm QB 3 1. 8 m QB 4 190 mm Foil Booster Gradient magnet 6 m 4 m (clearance) WBS 121. 05. 04 - Acc. U Booster Upgrade 11 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA 16 mm paint (start offset) 98 mm
Main Ring and BTL Crossing 3 B 0 Main Ring B 2 BTL, ARC 2 Charge #1 BTL, ARC 2 B 2 QFB 2 2 Main Ring B 0 3 B 0 B 3 QF B 3 1 B 0 PDR/CDR Design: Current Design: • 12 2 B 0 By using double strength dipole (B 3), instead of B 2 , in the Main ring beam line, we were able to eliminate the roll in the BTL beam line dipoles. 12/31/2021 • Use rolled dipoles not to interfere with the Main Ring beam line. 1 B 0 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Charge #1 the Beam Absorber Line (BAL) (PDR design) (current design) for future Mu 2 e to the Dump: 4 m The maximum bending angle: 0. 0155 rad H and V (38. 43 degree) 13 12/31/2021 Beam size @absorber (25 KW): round beam up to 5 mm M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Layout of Linac, BTL, BAL, and Mu 2 e Line (3 D CAD Model) Charge #1 Linac Booster BTL_ARC 1 Beam absorber Portable dump BAL BTL_ARC 2 Chute 14 12/31/2021 Mu 2 e line BTL M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Technical Progress to Date (2) - Beam Absorbers • Residual dose distributions calculated by MARS • Heat distributions calculated by ANSYS • Preliminary designs review completed on March 19, 2019 (PIP-II-doc-3429 -v 1) • Water cooling requirements were reduced due to lower power rating of the dumps Ø Tunnel absorber from 50 KW to 25 KW Ø Movable absorber from 5 KW to 2 KW 15 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA Charge #1
Technical Progress to Date (3) - Collimators • • 3 collimators: Horizontal, Vertical, Momentum (Horizontal) Preliminary design review completed on June 11, 2019 (PIP-II-doc-3426 -v 1) Cross section view (H) 16 Charge #1 12/31/2021 Cross section view (V) M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA Tunnel view
Cost Estimate 121. 05. 02 Acc. U – Beam Transfer Line and Beam Absorber 17 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA Charge #3, 6
Cost Performance Report Charge #3, 6 121. 05. 02 Acc. U – Beam Transfer Line and Beam Absorber • • BAC = $6, 413, 179 CPI=0. 84; SPI=0. 82 • Effort to redesign the lattice of the BTL was not expected. – – – 18 Construction strategy changed. The concern is about the impact to the Booster Enclosure. A solution of a Chute- a beam pipe will be utilized in the current design for the connection between the BTL and the Booster Making the lattice simpler by eliminate the rolls of the dipoles in the line. The concern is so many dipoles are rolled, it would bring the complexity of the magnet installation, and also the risk of the beam commissioning. The lattice is flat and optimized in the current design The lattice now is finalized 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Estimate Maturity • Estimate Uncertainty follows Project guidelines (PIP-II-doc-345) 19 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA Charge #3
Summary Schedule 20 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA Charge #3, 6
Charge #3, 6 FTE Breakdown Fabrication of collimators and Transfer line Absorber Manufacturing of Gamma Tjump 21 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Charge #8 ESH • All activities will be in full compliance with the PIP-II Integrated ESH Management Plan defined in PIP-II-doc-141 – Laboratory and DOE standards and practices • Fermi ES&H Manual, Radiological Control Manual, etc • Division/Area specific Hazards Analyses and Training • Personnel Safety and environmental and equipment protection are the highest priorities in the PIP-II Project. – included in all work via Prevention through Design Assessment – use marble to minimize the radiation exposure for both beam absorber and collimators. 22 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Quality Assurance • Incorporate quality in our design from the beginning (PIP-II-doc 2566). • Quality Control (QC) plans developed for each deliverable, Preliminary list of QC plans required – Lessons Learned Ex. Lessons learned from the muon campus beam absorber and Mini. Boone horn used in our design of the Beam dump. • Be sure that the dump can be serviced and replaced (use of rails) • Avoid materials that corrode and lead to fail (copper cooling lines) • Vendor management • Vendor QC Plans Required • • 23 Manufacturing Inspection/Test Plans Communication/Verification of requirements Vendor Visits Acceptance Testing 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
Summary • Requirements and Scope are understood • Interfaces are identified • Considerable progress in the design has been made since the last review – Beam line lattice optimized, Preliminary Design review is complete – Preliminary design for beam dumps and beam line collimators is complete • Cost and schedule have been developed and understood – EVMS tools are in place • ESH and QC plans are in place – Implementing lessons learned in the beam dump design • Project team is in place • We are ready for CD-2 and look forward to your feedback 24 12/31/2021 M. Xiao | 121. 05. 02 BTLBA | PIP-II DOE CD-2/3 a IPR - SC 2 - BTLBA
- Slides: 24