1 st Installation and Commissioning Workshop Forward Multiplicity

  • Slides: 13
Download presentation
1 st Installation and Commissioning Workshop Forward Multiplicity Detector (FMD) 6 October 2006 Borge

1 st Installation and Commissioning Workshop Forward Multiplicity Detector (FMD) 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Forward Multiplicity Detector (FMD) ITS Outer ring Inner ring FMD 1 6 October 2006

Forward Multiplicity Detector (FMD) ITS Outer ring Inner ring FMD 1 6 October 2006 FMD 2 Borge S. Nielsen, Niels Bohr Institute FMD 3

Detector elements Muon absorber cabling Final “Inner” Digitizer Final FMD 3 cone with beam

Detector elements Muon absorber cabling Final “Inner” Digitizer Final FMD 3 cone with beam pipe support Complete module (“outer” type) 6 October 2006 Borge S. Nielsen, Niels Bohr Institute Cone assembly test

System tests already done Mechanical assembly with models at CERN Beam tests with >5000

System tests already done Mechanical assembly with models at CERN Beam tests with >5000 active channels and 2 digitizer cards +1 RCU+DATE Full read-out tests with Digitizer+RCU+DATE 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Pre-commissioning • Pre-commissioning plans prior to installation @NBI: - assemble complete detectors (FMD 3

Pre-commissioning • Pre-commissioning plans prior to installation @NBI: - assemble complete detectors (FMD 3 + FMD 2, then FMD 1) - complete test with RCU, DDL, DATE, TTC/LTU, cooling (but not final CAEN LV and HV) - basic DCS panels, tested on simulated CAEN and real RCU/DCS card @CERN (Jan-Feb 2007): - retest as above, but with ‘final’ CAEN power supplies • Status of pre-commissioning (@NBI) - FMD 3 mechanics ~ready, FMD 2 starting production - all detector modules in house - TTC/LTU being set up - cooling plates in production - DCS work starting - complete read-out working 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Electronics & Racks • Locations of racks in the cavern + drawings of rack

Electronics & Racks • Locations of racks in the cavern + drawings of rack content including rack patch-panels and possible communication lines between racks and entry point of cables (top, bottom ? ) - Rack O 13 contains - Rack X 06 contains • Schedule for arrival of electronics and individual rack components at CERN. - Power supply crates - Power supply modules - Patch panels • one EASY 3000 crate with 48 V power supply etc one patch panel to distribute the LV cables from 10 digitizers and 3 RCUs to 4 low voltage modules one SY 1527 crate one patch panel to distribute the HV cables from 70 modules and 6 high voltage modules hopefully early 2007 before August 2007 – delivery schedule unknown to be mounted together with cable connectors Electronics commissioning - Power supplies to be installed and commissioned together with FMD 3 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Detector Arrival @ CERN Installation dates: FMD 3 16 -20 February 2007 FMD 2

Detector Arrival @ CERN Installation dates: FMD 3 16 -20 February 2007 FMD 2 07 March 2007 FMD 1 03 -05 July 2007 • When will the detector arrive at CERN ? - before mid January 2007 (FMD 3 and FMD 2, FMD 1 later) • What are the dimensions of the ‘transport cradle’ that must be brought to the place of installation ? How will it be brought there? - 2 times 1 x 1 x 1 m 3 by car • How many people will participate in the installation ? - 6 -8 people (physicists and technicians) • How many days before installation will the team arrive ? - early-mid January for lab. test: 3 -4 people - for installation: above + 3 -4 people 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Cables & Patch panels • Status of cable, fibre and connector ordering. - C

Cables & Patch panels • Status of cable, fibre and connector ordering. - C side cables on absorber done, remaining defined but cables not pulled. Fibres not pulled. - A side ~defined, but missing final cable lengths and final patch panel designs. • Plans for cabling, connector and cable testing activity by subgroup. - NBI: - cables on absorber and service chariot - all cable connectors - full cable testing - CERN: - pull long cables and all fibres • Needed patch panels and status of patch panels. - Still to be done: panels on A side (PP 2, PP 1, PP 0) panels in racks (LV and HV distributions) 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Installation (1) • Minimum status of services at start of installation. - all cables

Installation (1) • Minimum status of services at start of installation. - all cables and fibres ready and tested - LTU/TTC running - DAQ running - CAEN HV and EASY LV crates and ‘some’ modules delivered - preferably cooling water from TPC heat screen system • Installation tooling provided by the subdetector group. - support for cones during assembly • Other Infrastructure needed. - full ITS installation infrastructure • Installation scenario – day by day. - Before installation date: install and cable RCU modules - FMD 3: 3 days mechanical installation, then complete test - FMD 2: 1 day mechanical installation 1 day (12/03/2007) set aside for complete test after the cable hook-up 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Installation (2) • Tests and verifications during installation for cables, fibers and cooling lines.

Installation (2) • Tests and verifications during installation for cables, fibers and cooling lines. - cables etc should be tested before installation - FMD 3 should be verified through to the racks and counting rooms (with DCS and DAQ) - FMD 2 cannot be cabled until TPC is in place – ideally detector should be tested with the commissioning electronics; Not clear what is possible with temporary cabling, power etc. • Alignment requirements - assured at required precision by ITS installation scenario 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Commissioning – summary (1) At NBI: • Test all detector modules at NBI. –

Commissioning – summary (1) At NBI: • Test all detector modules at NBI. – • Pre-assembly at NBI – – – – – • Test inner and outer digitizers with. inner and outer detectors. S/N systematics Rate dependence System stability Limitations at NBI – • Cables Shielding (HF and light) Cooling Mechanical fit. Detectors, Honeycomb, Digitizer, beam tube support. Noise tests RO system w. 2 branches Calibration pulse test DCS control software Monitor software, test and calibration scripts. Check safety procedures (leakage current, auto shut off at beam injections, etc…) Final e-beam test at Aarhus – data taken 4 -5 November – – • Results stored in systematic fashion. Make list of repairs, send modules to CERN. Real LV and HV not available Final assembly at NBI - December 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Commissioning – summary (2) At CERN: • Detector operation at CERN in Lab. –

Commissioning – summary (2) At CERN: • Detector operation at CERN in Lab. – conditions similar to NBI lab. – – • Detector operation at CERN in Lab. – conditions similar to ALICE. – – • Exercise scripts to calibrate (pedestals, gain) and operate detector (start/stop/reset/load) Exercise first monitor programs Check stability and rate performance Check safety procedures (leakage current, auto shut off at beam injections, etc…) Preparation in ALICE (in pit) prior to installation – – – • Connect detectors to ‘real’ LV, HV, and trigger Establish DCS control of hardware Run with ‘real’ external trigger (LTU/TTC) and real ALICE DAQ Operate system in lab. Measure noise, stability and rate Calibration and Control procedures – – • (Re-) Assemble detector system after transport Connect detectors to LV, HV, and self-generated trigger Run with stand-alone DAQ Operate system in lab. Measure noise, stability and rate Verify all cables/connectors (long cables and local (PP-to detector) cables) Availability of trigger signal Availability of real HV, LV - LV situation problematic due to CAEN delivery schedule Availability of DCS control Availability of DAQ Installation (3 days for FMD 3, 1 day for FMD 2, 3 Days for FMD 1) - Run all scripts repeatedly and measure noise performance for entire system in situ (Requires HV, LV, Trigger and DAQ, partly DCS) 6 October 2006 Borge S. Nielsen, Niels Bohr Institute

Commissioning – summary (3) At CERN post installation: • Detector operation in ALICE. –

Commissioning – summary (3) At CERN post installation: • Detector operation in ALICE. – – • Connect detectors to ‘real’ LV, HV, and trigger Establish DCS control of final hardware Run with real external trigger (TTC) and real ALICE DAQ Operate system in ALICE. Measure noise and stability. Calibration and Control procedures – – – Exercise scripts to calibrate (pedestals, gain) and operate detector (start/stop/reset/load) Exercise first monitor programs Check stability and rate performance 6 October 2006 Borge S. Nielsen, Niels Bohr Institute