05100 Senior Design Project 05100 NonDestructive Joint Test

  • Slides: 30
Download presentation
05100 -- Senior Design Project 05100 – Non-Destructive Joint Test Method & Equipment Development

05100 -- Senior Design Project 05100 – Non-Destructive Joint Test Method & Equipment Development Sponsor: Delphi Automotive – Harrison Radiator Division Team Members: Aleksandra Soldo - IE - Team Leader Lauren Williams - IE Joshua Chan - ME Robert Lefferts - ME Elizabeth A. Kesel - ME Jason Mitchell - EE Thinh Cao - EE

05100 -- Senior Design Project Team Members Back (Left to right): Thinh Cao, Lauren

05100 -- Senior Design Project Team Members Back (Left to right): Thinh Cao, Lauren Williams, Robert Lefferts, Jason Mitchell Front (Left to right): Aleksandra Soldo, Elizabeth A. Kesel, Joshua Chan

05100 -- Senior Design Project Scope Develop a non destructive test method and equipment/tools

05100 -- Senior Design Project Scope Develop a non destructive test method and equipment/tools to verify the long term integrity of the clinch portion of a heater core pipe to neckshell assembly for an assembly process in a production environment. q Understand/Define the correlation between Joint Integrity and the pressure & temperatures at which they will leak. Develop a test method for production environment. q How to accurately measure clinch.

05100 -- Senior Design Project Long-term Objectives q Improve overall quality throughout the process

05100 -- Senior Design Project Long-term Objectives q Improve overall quality throughout the process by providing useful data and an accurate measurement system. q Reduce process variation to be more cost effective and efficient. q Help Delphi improve customer relations through improved product quality. 4

05100 -- Senior Design Project Parameters and Deliverables Clinch Measurement System q Must be

05100 -- Senior Design Project Parameters and Deliverables Clinch Measurement System q Must be non destructive. q Must be applicable to the HC 340 and all heater core assemblies. q The cost of equipment must not exceed $75, 000. q Must meet operator safety requirements as well as be ergonomically acceptable and environmentally friendly. q Must be integrated within the planned assembly/test process. q Equipment must pass MSA (measurement system analysis). q Must not adversely effect performance of joint or heater core assembly for use by the customer for the life of the product. q Must be in production by April 2005. q Test must be conducted within cycle time of production assembly (~20 sec). q Clinch vs. Leak Correlation q Statistical proof of correlation between clinch and leak.

05100 -- Senior Design Project Clinch Information 2. 0 MAX TYP NECK SHELL O-RING

05100 -- Senior Design Project Clinch Information 2. 0 MAX TYP NECK SHELL O-RING q q Delphi has a 2 mm maximum clinch gap specification. Each heater core has 2 joints. 3 clinches are used at each joint. Clinch gap is currently measured 4 times per shift by hand. Poor clinches are failed through physical inspection.

05100 -- Senior Design Project Testing Feasibility – Preparations Explained Test Plan 1 and

05100 -- Senior Design Project Testing Feasibility – Preparations Explained Test Plan 1 and 3 q q Delphi will randomly selected X number of “good” and “bad” heater cores from production throughout the duration of one week. (“good” meaning no clinch is > 2 mm, and core is not leaking. “Bad” meaning otherwise) For Test Plan 1, x =30 For Test Plan 2, x=90 (50 good, 40 bad) Ø 35 parts from each good/bad category will be randomly selected for the test. All 6 clinches on each core will be labeled, measured and recorded. Test Plan 2 q q q Delphi will randomly select a (large) number of “good” and “bad” heater cores from production throughout the duration of one week. (“good” meaning no clinch is > 2 mm, and core is not leaking “Bad” meaning otherwise) All 6 clinches on each core will be labeled, measured and recorded. Heater cores will be categorized according to measurements into one of the three “Gap-Ranges” n (Ranges n = 1, 2 or 3) Ø Range 1 (very bad clinches) – core have at least one clinch gap larger than 2. 5 mm Ø Range 2 (very good clinches) – core has all clinch gaps smaller than 1. 5 mm Ø Range 3 (middling clinches) – core doesn’t fall in the either one of the above categories Perform Leak test at room temperature for all the cores, and separate the cores that have a leak > 6 cc. Randomly select parts from category n for particular temperature/pressure combination.

05100 -- Senior Design Project Testing Feasibility – Procedures Explained Test parts sequentially at

05100 -- Senior Design Project Testing Feasibility – Procedures Explained Test parts sequentially at 25 psi, 35 psi, 45 psi, 55 psi at sequentially increased temperatures: (74º F, 175º F, 225º F, 250º F). All parts go together through the complete sequence of testing. Temperature 74º F Temperature 175º Temperature 225º F F Temperature 250º F (Plan 1) / -40º F (Plan 3) Pressure 25 psi X X Pressure 35 psi X X Pressure 45 psi X X Pressure 55 psi X X q X represents the number of cores used to testing. q All X are same, meaning each cell will contain results obtained from the same cores.

05100 -- Senior Design Project Testing Feasibility – Procedures Explained (cont. ) Test parts

05100 -- Senior Design Project Testing Feasibility – Procedures Explained (cont. ) Test parts randomly at 25 psi, 35 psi, 45 psi, 55 psi at temperatures randomly adjusted to 74º F 175º F, 225º F and 250º F. Each part exposed to only one set of conditions Temperature 1 Temperature 2 Temperature 3 Temperature 4 Pressure 1 Xn 12 Xn 13 Xn 14 Pressure 2 Xn 21 Xn 22 Xn 23 Xn 24 Pressure 3 Xn 31 Xn 32 Xn 33 Xn 34 Pressure 4 Xn 41 Xn 42 Xn 43 Xn 44 q Xnij stands for number of cores from Range n (n = 1, 2, or 3) that become exposed to the same pressure(i)/temperature(j) combination. q All X are same in size, meaning each cell will have same number of cores. (For X = 5 (meaning 5 cores per cell), and since n = 3 (meaning 3 gap ranges), and number of cells = 16 total number of cores needed would = 240. )

05100 -- Senior Design Project Feasibility Analysis Test Plan 1 (Base) Test Plan 2

05100 -- Senior Design Project Feasibility Analysis Test Plan 1 (Base) Test Plan 2 Test Plan 3 Resource Requirements 3 1 3 Sample Size Requirements 3 1 3 Quality of Statistical Analysis 3 5 3 Ranges 3 4 4 Ease of Test Performance 3 1 3 Total Rating 15 12 16 q Test Plan 1 is the “Base” with automatic ratings of 3. q The scale 1 -5 for individual ratings represents the ratings of 5 being the best and 1 being the worst Based on the ratings above the decision is to use Test Plan 3 as it has the highest total rating that is better than the Base.

05100 -- Senior Design Project Leak Test Procedure q Outlet pipe on all 70

05100 -- Senior Design Project Leak Test Procedure q Outlet pipe on all 70 heater cores are sealed with a rubber stopper and JB weld. q Heater cores are allowed to cure over night. 11

05100 -- Senior Design Project Testing Setup 12

05100 -- Senior Design Project Testing Setup 12

05100 -- Senior Design Project Testing Obstacles q The cores, not the clinches were

05100 -- Senior Design Project Testing Obstacles q The cores, not the clinches were leaking q There was too much movement in the heater core pipes causing stress in the clinch q Internal leaks in the measurement system q Un-calibrated equipment q Faulty equipment The mass flow meter we were using was not rated for our temperatures 13

05100 -- Senior Design Project Alternate Leak Test Setup Pressure decay test was setup

05100 -- Senior Design Project Alternate Leak Test Setup Pressure decay test was setup to use a flow meter acquired from Delphi Thermal & Interior Due to time constraints we never got this setup working properly 14

05100 -- Senior Design Project Testing Procedure q All 6 clinch gaps were measured

05100 -- Senior Design Project Testing Procedure q All 6 clinch gaps were measured using gauge pins q Outlet pipes were sealed with rubber stoppers secured with JB Weld q Gage R&R was performed on testing equipment 74º F 175º F 225º F - 40º F 25 psi -- -- 35 psi -- -- 45 psi -- -- 55 psi -- --

05100 -- Senior Design Project Testing Analysis q Minitab analysis q Regression analysis q

05100 -- Senior Design Project Testing Analysis q Minitab analysis q Regression analysis q Nonparametric analysis q Removed outliers q Box-Cox Transformation

05100 -- Senior Design Project Data Limitations q Limited Units for Testing q Given

05100 -- Senior Design Project Data Limitations q Limited Units for Testing q Given no memory effects in the cores, a single unit experienced all temperatures and pressures. q Time Constraints q Each unit experienced testing conditions in same order. Randomization, in this aspect, was not feasible. q Not able to take into account nuisance variables associated with day to day variance of testing equipment

05100 -- Senior Design Project Testing Analysis – Conclusions Bad part cut Difference between

05100 -- Senior Design Project Testing Analysis – Conclusions Bad part cut Difference between bad and good part leak rates -off (outliers included) Good-Bad 2. 0 mm (current) 2. 5 mm (0, . 3) sccm 3. 0 mm (. 04, . 7 sccm) (0, . 3) sccm

05100 -- Senior Design Project Testing Analysis – Conclusions (cont. ) q There is

05100 -- Senior Design Project Testing Analysis – Conclusions (cont. ) q There is a positive relationship between median values of leak rate for each pressure and the values vary between. 55 sccm and 1. 2 sccm. q Whether or (the average left pipe clinch gap) account for about 16% of the variability in leak rate with outliers and 46. 4% without them. q The ANOVA and regression assumptions of identically distributed sample populations are grossly violated in the original model, but are borderline acceptable with Box-Cox transformed data. q Comparing the room temperature leak rates shows that the parts have the same leak rates before and after the temperature extremes and there may be reason to believe there are no “memory” effects due to prior testing.

05100 -- Senior Design Project Suggested Future Test Plan Example Core # Temperature (F)

05100 -- Senior Design Project Suggested Future Test Plan Example Core # Temperature (F) Pressure (psi) Clinch Gap 32 175 45 C 18 225 35 A 47 75 35 B 2 175 55 A 16 -40 25 C 43 225 45 B 11 75 25 B 38 -40 55 A Leak Rate And so on until each treatment combination has been tried n times

05100 -- Senior Design Project Camera System Verification q Camera system was mounted and

05100 -- Senior Design Project Camera System Verification q Camera system was mounted and calibrated (X and Y axis) with a distance of 6. 5 inches. q Heater cores were placed and images taken and measured. q Three different operators of system to get repeatability and reproducibility. q Measurements recorded and entered in Gage R&R spreadsheet from Delphi.

05100 -- Senior Design Project Financial Analysis for Clinch Measurement System q Delphi allocated

05100 -- Senior Design Project Financial Analysis for Clinch Measurement System q Delphi allocated $75, 000 for system q Cost of CV-2100 Vision System: $8, 000 -$11, 000 q Two systems will be required q Total Implementation Cost: $16, 000 -$22, 000 q Minimum percentage of budget: 21% q Maximum percentage of budget: 29% q System is within budget

05100 -- Senior Design Project Accomplishments & Conclusions q Developed an understanding of project

05100 -- Senior Design Project Accomplishments & Conclusions q Developed an understanding of project definition and scope q Developed concepts to meet project deliverables q Completed feasibility assessment q Presented preliminary design concepts in front of a panel q Completed testing feasibility q Conducted testing q Performed extensive statistical analysis q Gave sponsor documented information about their problem q Proposed a future course of action for sponsor

05100 -- Senior Design Project Additional Questions?

05100 -- Senior Design Project Additional Questions?

05100 -- Senior Design Project Metal Memory Test One-Sample T: D 25, D 35,

05100 -- Senior Design Project Metal Memory Test One-Sample T: D 25, D 35, D 45, D 55 P/N 25 PSI before 25 PSI after D 25 35 PSI before 35 PSI after D 35 45 PSI before 45 PSI after D 45 55 PSI before 55 PSI after D 55 0. 2 0. 5 0. 3 0. 6 0. 7 0. 1 0. 6 0. 5 -0. 1 0. 7 0. 9 0. 2 Variable N Mean St. Dev SE Mean 4 b 0. 7 0. 3 -0. 4 1. 0 0. 9 -0. 1 1. 2 1. 4 0. 2 1. 4 1. 9 0. 5 D 35 10 0. 130 0. 330 0. 104 22 g 0. 4 0. 6 0. 2 0. 9 0. 8 -0. 1 1. 4 1. 5 0. 1 1. 7 2. 1 0. 4 D 55 10 0. 110 0. 486 0. 154 11 g 1. 0 0. 8 -0. 2 1. 1 1. 0 -0. 1 1. 8 1. 5 -0. 3 2. 2 1. 7 -0. 5 Variable 95. 0% CI T P 19 b 0. 5 0. 7 0. 2 0. 6 0. 7 0. 1 0. 6 0. 9 0. 3 0. 7 1. 0 0. 3 37 b 0. 9 0. 7 -0. 2 0. 9 1. 2 0. 3 1. 1 1. 2 0. 1 1. 3 0. 7 -0. 6 34 b 1. 7 2. 2 0. 5 2. 3 3. 2 0. 9 3. 6 4. 0 0. 4 4. 8 5. 7 0. 9 18 g 0. 6 0. 3 -0. 3 0. 8 0. 0 0. 9 1. 1 0. 2 1. 0 1. 4 0. 4 8 g 0. 8 0. 6 -0. 2 1. 0 0. 8 -0. 2 1. 1 0. 9 -0. 2 9 b 0. 2 0. 5 0. 3 0. 7 1. 1 0. 4 1. 3 1. 1 -0. 2 1. 5 1. 2 -0. 3 21 b Test of mu = 0 vs mu not = 0 D 25 10 0. 0200 0. 3120 0. 0987 D 45 10 0. 0500 0. 2369 0. 0749 D 25 ( -0. 2032, 0. 2432) 0. 20 0. 844 D 35 ( -0. 106, 0. 366) 1. 25 0. 245 D 45 ( -0. 1195, 0. 2195) 0. 67 0. 521 D 55 ( -0. 238, 0. 458) 0. 72 0. 493

05100 -- Senior Design Project Clinch Gap Correlation Mood Median Test: Leak Rate (Sccm)

05100 -- Senior Design Project Clinch Gap Correlation Mood Median Test: Leak Rate (Sccm) versus Has Bad Clinch Mood median test for Leak Rate Chi-Square = 7. 43 DF = 1 P = 0. 006 Individual 95. 0% CIs Has Bad N<= N> Median Q 3 -Q 1 -+---------+-----+----0 83 44 0. 800 0. 500 +-----) 1 56 1. 000 0. 600 (-----+-----) -+---------+-----+---- 0. 80 0. 90 1. 00 1. 10 Overall median = 0. 900 A 95. 0% CI for median(0) - median(1): (-0. 300, 0. 000)

05100 -- Senior Design Project Clinch Gap Correlation (cont).

05100 -- Senior Design Project Clinch Gap Correlation (cont).

05100 -- Senior Design Project Pressure Correlation Leak Rate (Sccm) = 0. 0465 +

05100 -- Senior Design Project Pressure Correlation Leak Rate (Sccm) = 0. 0465 + 0. 0217 Pressure (psi) Predictor Coef SE Coef T P Constant 0. 04646 0. 07393 0. 63 0. 530 Pressure 0. 021700 0. 001783 12. 17 0. 000 S = 0. 2971 R-Sq = 40. 1% R-Sq(adj) = 39. 9% Analysis of Variance Source DF SS MS F P Regression 1 13. 078 148. 12 0. 000 Residual Error 221 19. 514 0. 088 Total 222 32. 592 Mood median test for Leak Rate Chi-Square = 70. 19 DF = 3 P = 0. 000 Individual 95. 0% CIs Pressure N<= N> Median Q 3 -Q 1 -----+---------+-----25 51 5 0. 550 0. 300 (-+-) 35 43 13 0. 800 0. 200 (---+ 45 30 26 0. 900 0. 300 +--) 55 10 45 1. 200 0. 500 (+----) -----+---------+----- 0. 75 1. 00 1. 25 Overall median = 0. 900 223 cases were used 4 cases contained missing values Kruskal-Wallis Test on Leak Rate Pressure N Median Ave Rank Z 25 56 0. 5500 53. 9 -7. 78 35 56 0. 8000 97. 1 -2. 00 45 56 0. 9000 125. 8 1. 84 55 1. 2000 172. 3 7. 98 Overall 223 112. 0 H = 98. 94 DF = 3 P = 0. 000 H = 99. 75 DF = 3 P = 0. 000 (adjusted for ties)

05100 -- Senior Design Project Box-Cox Transformation

05100 -- Senior Design Project Box-Cox Transformation

05100 -- Senior Design Project Verification of ANOVA

05100 -- Senior Design Project Verification of ANOVA